**1. Introduction**
1.1. The Pyrite Remediation Programme is a national scheme to remediate dwellings affected by pyrite heave.
1.2. The Programme is funded by the Department of Housing, Local Government and Heritage.
**2. Purpose**
2.1. The purpose of this notice is to establish a multi-disciplinary Contractor Framework for the delivery of the Pyrite Remediation Programme.
2.2. The Contractor Framework will be used to appoint contractors to carry out remedial works to dwellings affected by pyrite heave.
**3. Scope of Works**
3.1. The scope of works to be carried out under this Contractor Framework will include, but not be limited to, the following:
- Site investigation and assessment
- Design of remedial works
- Execution of remedial works
- Monitoring and maintenance of remedial works
3.2. The Contractor Framework will be used to appoint contractors for the following disciplines:
- Civil/Structural Engineering
- Geotechnical Engineering
- Building Surveying
- Architecture
- Quantity Surveying
**4. Contractor Framework**
4.1. The Contractor Framework will be established for a period of 4 years from the date of award.
4.2. The Contractor Framework will be operated on a call-off basis, with contractors being appointed for individual projects as required.
4.3. The Contractor Framework will be open to contractors who meet the selection criteria and who have been pre-qualified.
4.4. The selection criteria will include, but not be limited to, the following:
- Relevant experience and expertise
- Financial and technical capacity
- Health and safety record
- Environmental management record
4.5. Contractors will be pre-qualified through a competitive selection process.
4.6. The Contractor Framework will be advertised on the eTenders website.
4.7. The Contractor Framework will be subject to the Public Works Contracts.
**5. Contractor Obligations**
5.1. Contractors appointed under the Contractor Framework will be required to:
- Comply with the terms and conditions of the Contractor Framework
- Carry out the works to the required standard and within the specified timeframe
- Comply with all relevant health and safety regulations
- Comply with all relevant environmental regulations
- Provide regular progress reports to the Programme Manager
- Maintain accurate records of all works carried out
- Cooperate with other contractors and stakeholders
**6. Programme Management**
6.1. The Programme will be managed by a dedicated Programme Management Office (PMO).
6.2. The PMO will be responsible for the overall management and coordination of the Programme, including:
- Project management
- Contract management
- Quality assurance
- Health and safety management
- Environmental management
- Stakeholder management
6.3. The PMO will be supported by a team of technical experts in the relevant disciplines.
6.4. The PMO will be based in the Department of Housing, Local Government and Heritage.
**7. Contact Details**
7.1. For further information, please contact:
Programme Management Office
Department of Housing, Local Government and Heritage
Newtown House
Newtown
Wexford
Y35 DY72
Email: [email protected]
Website: https://www.gov.ie/en/organisation/department-of-housing-local-government-and-heritage/
**8. References**
8.1. Public Works Contracts
8.2. eTenders website
8.3. Department of Housing, Local Government and Heritage website
CPV-koder
Dokument & inlämning
Contains data from Tenders Electronic Daily (TED), © European Union, ted.europa.eu — CC BY 4.0.
Liknande upphandlingar
Ireland – Construction work – 22 Heatherview Close, Dublin D24 WKD0.
Cheeverstown HouseIrlandConstruction workDeadline om 17 dagarPublicerad den 19 nov. 2026
Ireland – Refurbishment of run-down buildings – Refurbishment and Adaptive Re-use of West Gate House and Drogheda Youth Development Building
Louth County Council_381IrlandRefurbishment of run-down buildingsBuilding construction workBuildings of particular historical or architectural interestIngen frist angivenPublicerad den 19 nov. 2026
Ireland – Footpath construction work – Erris Looped Walks, Corclough Village, Mullet Peninsula, Co. Mayo
Údarás Na Gaeltachta_289IrlandFootpath construction workBoardwalk construction workPedestrian ways construction workDeadline om 45 dagarPublicerad den 19 nov. 2026
Ireland – Engineering works and construction works – FIRE REMEDIAL AND REINSTATEMENT WORKS AT MARYMOUNT UNIVERSITY HOSPITAL AND HOSPICE
Marymount University Hospital and HospiceIrlandEngineering works and construction worksDeadline om 31 dagarPublicerad den 19 nov. 2026