Description
1. Background and damage assessment
The CBS building complex at Solbjerg Plads has, since its construction around the year 2000, been affected by leaks in the facades and roof. Water ingress has been identified in parts of buildings A, B, and C to the south, as well as in buildings D and F. At present, no water ingress has been registered in the remaining parts of the building complex.
The Technological Institute has, in the period 2022–2024, conducted physical inspections and analyses of the roofs and facades at various locations in the buildings. The investigations have revealed construction defects that can be attributed to the buildings' construction. Significant degradation of organic materials and joints in the facades has also been noted. The conditions do not pose an immediate structural risk but entail an increased future risk of further water ingress in the building sections that are not renovated.
2. Scope of the tender and contract form
The task is tendered as a total enterprise, where the Total Contractor has the overall responsibility for design and execution within the framework and functional requirements set out in the tender material.
This tender includes the design and improvement of selected parts of the facades and roofs of the CBS building complex at Solbjerg Plads.
The task concerns a renovation project that must be carried out while the buildings are in operation. This places special demands on planning, coordination, and management of the workers' execution, so that the work is completed on time, to the agreed quality, and with the least possible inconvenience to the building's users.
3. Early contractor involvement and phase division
The contract is executed with early contractor involvement and is divided into two phases:
Phase 1 – Design of all stages and execution of stage 1
In Phase 1, the Total Contractor designs all stages (stage 1–4). Furthermore, stage 1 is executed. The design and execution are based on the Total Contractor's fixed-price offer, which covers both phases and all stages.
Phase 2 – Adjusted design and execution of stages 2–4
Phase 2 includes any correction and adjustment of the project material for stages 2–4 based on the experiences from the execution of stage 1, as well as the subsequent execution of these stages.
The client expects that the early execution of stage 1 will generate valuable knowledge that can be used to optimize both the design, planning, and execution of the remaining stages.
4. Knowledge transfer and decision basis for phase 2
Before initiating Phase 2, the Total Contractor must report on the possibilities for optimization and integration of experiences from stage 1, including describing the economic and time-related consequences of any adjustments.
Based on this, the Total Contractor submits an offer regarding:
Correction and adjustment of the project material for stages 2–4, and
Execution of Phase 2.
The offer must be submitted based on the unit prices that appear in or can be derived from the Total Contractor's original offer. Phase 2 is initiated only after the client's written acceptance of the offer.
CPV codes
Documents & submission
Contains data from Tenders Electronic Daily (TED), © European Union, ted.europa.eu — CC BY 4.0.
Related tenders
Denmark – Pipelaying construction work – Fjernvarmeforsyning af Båring og Asperup
Middelfart Fjernvarme a.m.b.a.DenmarkPipelaying construction workDistance-heating pipesNo deadline givenPublished on Oct 21, 2026
Denmark – Construction work – BoVendia, afd. 8 – Karolinesvej, Lonesvej og Mettesvej
BoVendia, afd. 8DenmarkConstruction workNo deadline givenPublished on Oct 21, 2026
Denmark – District-heating plant construction work – Levering og etablering teknikbygning til Stoholm Fjernvarmeværk a.m.b.a.
Stoholm Fjernvarmeværk a.m.b.a.DenmarkDistrict-heating plant construction workHeat pumpsDeadline in 29 daysPublished on Oct 20, 2026
Denmark – Works for complete or part construction and civil engineering work – Hovedentreprise vedrørende transformation af dele af Det Kongelige Palæ og den tilhørende Palæhave til Roskilde Domkirke Verdensarvscenter
Ejendomsfonden Roskilde Domkirke VerdensarvscenterDenmarkWorks for complete or part construction and civil engineering workExhibition centre construction workBuilding construction workNo deadline givenPublished on Oct 20, 2026