France – Construction work for railways and cable transport systems – EOLE Mantes phases cible
Description
Earthworks, Drainage, Catenary / General Civil Engineering / Buildings / Platforms / Artworks, divided into 4 phases (Preparation Phase 5, and Phases 5, 6 and 7). The main works of the firm section are:
• Remodelling of the track layout of the Northern Bottleneck (GrVI tracks, V2GrV and Le Havre tracks);
• Commissioning of the Leapfrog connecting the Le Havre tracks to the Caen tracks (future V2C);
• Remodelling of the track layout of Mantes La Jolie Sud (V1Bis, V1GrV, Special tracks, Caen tracks, Service tracks of the Plaine Bundle and Buchelay Bundle Entrance);
• Commissioning of the Piquettes Connection connecting the Caen tracks to the Le Havre tracks (future V1H);
• Demolition of Buildings (Post, Centre, Satellites) following the commissioning of PAI 45 and 46;
• Reorganisation of the Mantes La Jolie Quays (Ends of Quay 2D, Raising of Quay 3, Reconstruction of Quay 4) and Mantes Station (Quay nose repair and installation of EAS systems);
• Catenary removal and connection works in the Bottleneck, Piquettes Connection and Leapfrog;
• Foundations and Installation of the new Mantes-La-Jolie footbridge.
Place of execution: Mantes-La-Jolie, Issou, Porcheville, Épône-Mézières, Guerville, Rosny-sur-Seine.
CPV codes
Documents & submission
Contains data from Tenders Electronic Daily (TED), © European Union, ted.europa.eu — CC BY 4.0.
Related tenders
France – Wall-covering work – Accord-cadre à bons de commande pour des travaux d'entretien courant de Peinture Revêtements Muraux et Revêtements de sols
OPH de la Haute-SaôneFranceWall-covering workFloor-covering workDeadline in 44 daysPublished on Sep 08, 2026
France – Installation of road lighting equipment – Travaux de Génie Electrique sur le territoire de Grand Besançon Métropole
Grand Besançon MétropoleFranceInstallation of road lighting equipmentInstallation of outdoor illumination equipmentDeadline in 33 daysPublished on Sep 08, 2026
France – Wall-covering work – Accord-cadre à bons de commande en multi-attribution pour des travaux d'entretien courant de peinture et revêtements muraux
OPH de la Haute-SaôneFranceWall-covering workDeadline in 44 daysPublished on Sep 08, 2026
France – Floor-covering work – Accord-cadre à bons de commande en multi-attribution pour des travaux d'entretien courant de revêtements de sols
OPH de la Haute-SaôneFranceFloor-covering workDeadline in 44 daysPublished on Sep 08, 2026