Germany – Airport buildings construction work – 2026-1005079_Flughafen München_Generalübernehmer Gepäcksortierhalle Terminal 1 auf Pos. 113

Flughafen München GmbHGermanyPublished on Oct 14, 2026
No deadline given

Description

Within the T/EINS program, Terminal 1 of Munich Airport is being gradually modernized to ensure safe and efficient operations until at least 2050. Since the existing baggage handling system will only be partially available during the renovation, additional baggage infrastructure is required to maintain baggage operations. For this purpose, a new baggage sorting hall (GSH-113) will be constructed at apron position 113. The hall complements the existing baggage logistics of Terminal 1 and will be directly connected to the existing baggage handling system. It will handle central functions of baggage handling such as sorting, security checks, manual rework, customs checks, and the reintroduction of baggage into the ongoing conveying process.

Building Concept

The baggage sorting hall will be designed as a single-story operational building with an additional steel intermediate level for conveying technology and technical systems. The building will have a functional building envelope with a sandwich facade and a flat roof. The total gross floor area, including technical and ancillary areas, as well as the grid floor, will be approximately 6,000 m². The building height will be about 9 m and can locally reach up to 12 m due to technical superstructures.

Operation and Capacity

The facility is designed for a sorting capacity of up to 2,500 items of baggage per hour and provides the necessary capacity to ensure baggage operations during the comprehensive renovation of Terminal 1. In addition to sorting and inspection areas, spaces for operations, personnel, storage, and technology are provided.

Project Organisation and Procurement

The overall measure is to be implemented in several procurement units. The plan is to commission a general contractor for the planning and construction of the baggage sorting hall, including the grid floor, a general contractor for the supply and construction of the baggage handling system, and a separate contractor for connecting the hall to the existing structure (bridge structure). This will ensure that the respective specialist trades are efficiently implemented and the interfaces between the structure and the baggage handling technology are specifically controlled.

Location and Framework Conditions

The baggage sorting hall will be constructed on a free apron area in the safety-critical area of Munich Airport. The construction site contains existing infrastructure lines, including fuel lines, drainage systems, as well as power and IT lines. In addition, there is a direct spatial proximity to the existing buildings of Terminal 1 and Hall C-West.

Interfaces

The project has technical and operational interfaces with the existing buildings, supply and disposal systems, and the comprehensive renovation of Terminal 1. Furthermore, a charging point for apron vehicles is planned southeast of the baggage sorting hall. Synergies in the power supply will be examined as part of the planning.

Energy Supply and Sustainability

The hall will be designed as a fully functional operational building with its own technical supply. The legal requirements for energy efficiency will be met. Use is planned for at least until the completion of the renovation of Terminal 1 (at least 12 years); further usage periods will be examined in the further course of the project.

Special Framework Conditions

The new construction will take place in the safety-critical apron area of Munich Airport during ongoing flight operations. The planning and execution must take into account the requirements of airport operations, aviation security, and the maintenance of adjacent operational processes. Construction and logistics processes are subject to special safety, access, and approval requirements. Existing supply lines in the construction site must be taken into account during construction and appropriately integrated into the operational concepts.

Dates

The following project-relevant milestones are specified for the planning and realization of the measure:

- Execution of planning services in phases 3 to 5: presumably Q2/2027 to Q4/2027

- Start of construction: presumably Q1/2028

- Completion of construction including full commissioning of the technical building equipment: by Q2/2029 at the latest

The aforementioned dates represent the current project target planning of the client and must be taken into account by the contractor in their scheduling and resource planning. The contractor must organize their planning, approval, procurement, and execution processes in such a way as to ensure compliance with the specified milestones. To this end, a continuous schedule management including regular progress control and reporting must be provided.

Overall Objective

With the GSH-113, a high-performance and operationally integrated extension of the baggage logistics of Terminal 1 will be created. It ensures the maintenance of baggage handling during the extensive modernization measures and supports a safe and economical airport operation.

CPV codes

Airport buildings construction workConstruction work for industrial buildingsBuilding installation workArchitectural, engineering and planning services

Documents & submission

AI summary
Sign in for an AI summary

Contains data from Tenders Electronic Daily (TED), © European Union, ted.europa.eu — CC BY 4.0.

Related tenders