Road maintenance is an activity to ensure the necessary conditions for continuous, safe and convenient movement along them and to protect them from premature wear. The activities for the current maintenance of roads, depending on the goals to be achieved, are divided into: - preventive maintenance; - current / routine maintenance; - current repair; - emergency restoration work in emergency situations. The types of work are given in tabular form as follows:

| № | Type of Work | Unit |

| 1 | Removal of asphalt pavement | m³ |

| 2 | Cutting of asphalt pavement with a cutting machine | m |

| 3 | Demolition of concrete sidewalk | m² |

| 4 | Demolition of concrete curbs | m |

| 5 | Demolition of concrete stripes | m |

| 6 | Removal of non-reinforced concrete | m³ |

| 7 | Removal of reinforced concrete | m³ |

| 8 | Excavation of earth masses - mechanical | m³ |

| 9 | Excavation of earth masses - manual | m³ |

| 10 | Levelling and compacting of earth bed according to template | m³ |

| 11 | Delivery and laying of loose asphalt concrete | t |

| 12 | Delivery and laying of dense asphalt concrete | t |

| 13 | Delivery and making of base with crushed stone 0-63 mm | m³ |

| 14 | Delivery and making of base with crushed stone 0-40 mm | m³ |

| 15 | Delivery and laying of reinforced concrete | m³ |

| 16 | Making of asphalt patches with manual cutting and manual laying of dense asphalt concrete with a thickness of 4 cm and all related activities | m² |

| 17 | Making of asphalt patches with manual cutting and manual laying of dense asphalt concrete with a thickness of 5 cm and all related activities | m² |

| 18 | Making of asphalt patches with manual cutting and manual laying of dense asphalt concrete with a thickness of 6 cm and all related activities | m² |

| 19 | Making of asphalt patches with manual cutting and manual laying of dense asphalt concrete with a thickness of 7 cm and all related activities | m² |

| 20 | Making of asphalt patches with manual cutting and manual laying of dense asphalt concrete with a thickness of 8 cm and all related activities | m² |

| 21 | Making of asphalt patches with manual cutting and manual laying of dense asphalt concrete with a thickness of 9 cm and all related activities | m² |

| 22 | Making of asphalt patches with manual cutting and manual laying of dense asphalt concrete with a thickness of 10 cm and all related activities | m² |

| 23 | Milling of old asphalt concrete pavement | m² |

| 24 | Edging of the patch with bitumen paste, incl. cleaning and blowing of joints | m |

| 25 | Making of concrete curbs 15/20/50 cm, including delivery of materials | m |

| 26 | Making of concrete curbs 18/35/50 cm, including delivery of materials | m |

| 27 | Making of concrete guide stripes, including delivery of materials | m |

| 28 | Making of pavement from "beha-ton" paving stones, including all related costs | m² |

| 29 | Installation of tactile plates, including delivery of materials | m² |

| 30 | Making of pavement from concrete slabs 40/40/5 cm (with slabs from the site) | m² |

| 31 | Making of pavement from concrete slabs 40/40/5 cm, including delivery of materials | m² |

| 32 | Making of linear drain, incl. connection with runoff and sewerage | m |

| 33 | Raising of rainwater inlet, including delivery of materials | no. |

| 34 | Raising of inspection shaft, including delivery of materials | no. |

| 35 | Raising of electrical shaft, including delivery of materials | no. |

| 36 | Making of single simple street outlet | no. |

| 37 | Making of channel 200 for securing street outlets in inspection shaft | m |

| 38 | Backfilling of excavation | m³ |

| 39 | Making of locking grid on street outlet (set with frame) | no. |

| 40 | Collection, transportation, loading and disposal of construction and other waste | m³ |

A detailed description of all the envisaged activities is contained in the technical specification attached to the documentation.

CPV codes

Surface work for streetsFoundation work for streets

Documents & submission

AI summary
Sign in for an AI summary

Contains data from Tenders Electronic Daily (TED), © European Union, ted.europa.eu — CC BY 4.0.

Related tenders