Belgium – Medical equipments – Levering, plaatsing en indienstelling van PET CT
Description
Explanation: Purchase, delivery and installation of a PET CT scanner, including table, all device-specific works (server space, techniques, cooling), hardware and software and further finishing of the space. The current PET-CT is approaching the end of its technical lifespan and has insufficient capacity to adequately meet the current demand for PET-CT examinations. The demand for PET-CT examinations is expected to continue to grow. Furthermore, the resolution of the scanners is no longer state-of-the-art. For the new system, we are looking for a high-end PET/CT scanner that enables us to carry out high-quality PET/CT research, both clinically and scientifically. Since AZORG has more than 1 PET CT and this will be unavailable to patients during the works, we wish to emphasize that limiting downtime in this entire project is very important. AZORG therefore expects a quick execution, good coordination and smooth cooperation between the various contractors and our own construction team.
Equipment + equipment-bound works: (PLEASE ADAPT SPECIFICATIONS! is a copy from the previous dossier from 2017)
• High-end volume PET CT scan, minimum 16 acquisition slices.
• System sensitivity ≥ 7.5 cps/kBq, measured according to the NEMA-2007 standard.
• Possibility of variable acquisition parameters within the same PET-acquisition is included.
• It is possible to synchronize acquisitions with the time of injection.
• The possibility to reconstruct the images again (and possibly in a different way) after the date.
• Possibility to automatically archive reconstructed images on PACS.
Image quality
• System sensitivity ≥ 7.5 cps/kBq, measured according to the NEMA-2007 standard.
• TOF – Time of Flight.
• A flat radiotherapy bed is included.
• The presence of an external laser for radiotherapy.
Maintenance
• The warranty period is 2 years.
• During the warranty period, the full omnium maintenance contract (maintenance, interventions, repairs …) is fully at the expense of the supplier.
• The installation and execution of software updates are included in the omnium maintenance contract. The tenderer guarantees that it will always be able to work with the latest software version with the newest possibilities of the already purchased software packages for at least 7 years after the installation date.
Training
• The tenderer provides sufficient training and training for doctors, nurses and physicists of the department, as well as for technicians of each hospital. A plan of approach and measures to guarantee this continuous support must be submitted.
Equipment-bound works
* In this project, the equipment-specific works will also be carried out for the supplier. This includes: site preparation and site follow-up, electrical works necessary to run the equipment, floor and ceiling works, installation of the server space, cooling, all necessary pipes, cabling, alarms and all necessary inspections and certificates for the delivery of the new equipment. All mandatory inspections and certificates must be included in the tender. The taking into use of buildings or parts thereof does not constitute delivery of the works. Delivery, placement, connection, commissioning and testing of all parts of the installation are always included.
Building works
The techniques are carried out by the main contractors via framework agreements. The building works are included in this dossier as well as the placement of lead shielding in the room. The new equipment will be placed on Campus Moorselbaan, at the department of nuclear medicine, to replace the current PET CT. All mandatory inspections and certificates must be included in the tender. The tenderer acknowledges Appendix M: General safety and health plan AZORG and confirms to comply with this by returning it signed. The contractor takes all necessary measures to avoid damage to existing infrastructure and completely excludes dust nuisance within the building. During the works, existing, delivered and installed materials are protected against damage, weather influences and theft. The taking into use of buildings or parts thereof does not constitute delivery of the works. Delivery, placement, connection, commissioning and testing of all parts of the installation are always included.
Old PET CT take-over or dismantling
AZORG no longer wishes to use the old PET CT. The removal of the old CT equipment is included in a separate lot. This can either be by a takeover of the old Siemens equipment dating from 2018 or by a dismantling and scrapping of the old equipment with a certificate and according to the applicable regulations. The contractor also provides a crane or other necessary tools to make this possible. In the timeline of this dossier, this lot will be executed first before other works can begin.
CPV codes
Documents & submission
Contains data from Tenders Electronic Daily (TED), © European Union, ted.europa.eu — CC BY 4.0.
Related tenders
Belgium – Pharmaceutical products – Accord-cadre pluri-attributaire relatif à la fourniture d’ONDANSETRON – NETUPITANT+PALONOSETRON - APREPITANT pour les besoins des pharmacies de Vivalia
VivaliaBelgiumPharmaceutical productsDeadline in 53 daysPublished on Nov 19, 2026
Belgium – Medical consumables – LEVERINGEN VAN MEDISCHE PERSOONLIJKE BESCHERMINGSMIDDELEN
UZ LeuvenBelgiumMedical consumablesSafety visorsProtective gearNo deadline givenPublished on Nov 19, 2026
Belgium – Pharmaceutical products – Accord-cadre pluri-attributaire relatif à la fourniture de Fer III Carboxymaltose injectable pour les besoins des pharmacies de Vivalia
VivaliaBelgiumPharmaceutical productsDeadline in 53 daysPublished on Nov 19, 2026
Belgium – Pharmaceutical products – Raamovereenkomst voor het leveren van medicatie voor het gastro-intestinaal stelsel
Hospilim VZWBelgiumPharmaceutical productsVarious medicinal productsMedicinal products for the alimentary tract and metabolismDeadline in 32 daysPublished on Nov 19, 2026